FLAME 2017: TAP nearly half built as olive trees cleared
Publication date: 12 May 2017
Gas Strategies Group
10 Saint Bride Street
London UK
EC4A 4AD
ISSN: 0964-8496
Twitter @GasStrategies
Editorials
Subscriptions
Construction of the Trans-Adriatic Pipeline is nearing the mid-way point and works on the landfall in Puglia have resumed following the lifting of a court order that was protecting olive trees along the route.
Speaking to Gas Matters Today on the side-lines of Flame conference in Amsterdam on Thursday, TAP commercial and external affairs director Ulrike Andres said the pipeline is “currently about 40% built”.